© 2007 Dr. Ray Franco, PhD., PE r.a.franco@ieee.org
Entergy of Mississippi is changing the wood poles on the transmission line South of Batesville, MS to concrete poles. The old HX Frames were original constructed for a single 115 KV line. However, as the demand for electricity increased, the line was changed to a 230 KV line and then to double 230 KV lines. On 3 March 2007, I photographed the Pike Electric crew changing out one of the poles.
For Maximum Resolution, Click on the Body of the Picture.
First, the Lines are de-energized and then Protective Safety Grounds are placed on the First Pole Upstream.
An Equal-Potential Zone is established. Cable Ties are removed from the Center Line, Which will be moved to the Pole on the Right.
The Auger Truck Grabs the Pole so the Crane Operator can assist Others While the Cement is Currying.
The Cross Member of the H-Frame is removed, While another Crew Member connects the Pole Ground to the Shield Wires.